IXOM Chemicals, Port Botany, Sydney
Sept 15 - Ongoing
Scope of works:
Bulk Stockpile, Batter creation, traffic management, truck decontamination.
Project Highlights:
35,000 ton stockpiled in 36hr window every 6 months
Western Sydney Airport Visitor Centre
Jan 2019 - March 2019
Scope of works:
Site establishment, installing erosion & sediment controls, site compound, removal of Asbestos Contaminated Material (ACM), stockpiling, capping, and vegetation.
Project Highlights:
Safe handling & capping of 30tonnes of ACM
Sydney Metro 2, Waterloo Station Earthworks
Nov 18 - March 2019
Scope of works:
Excavation of shaft with long reach 55ton excavtor, rock breaking with D11 Dozer, stockpiling and loading trucks.
Project Highlights:
Shaft completed in time for arrival of TBM.
Caltex Refinery, Solander Street, Kurnell NSW
April 2019 - August 2019
Scope of works:
Asbestos removal, on-site capping, and storage of Asbestos Contaminted Material
Project Highlights:
Pipeway A, Pipeway B and Main pipeway completed on schedule and incident-free.
M1 Upgrade, Kariong to Somersby
Feb 19 - July 2019
Scope of works:
Crushing waste onsite materials and processing into a reusable product.
WESTERN SYDNEY AIRPORT EARLY EARTHWORKS
Nov 18 - ongoing
Scope of works:
Site Remediation, bulk earthworks, haulage, stock management, trenching, erosion & sediment controls.
Caltex Refinery Kurnell
Jul 16 - Aug 18
Scope of works:
Demolition, bulk earthworks, road repairs, drainage, regading, stockpile management and materials haulage.
Western Sydney Airport Visitor Centre
Mar 19 - July 19
Scope of works:
bulk earthworks, regrading, trenching, piling, installation of services, concreting and asphalting.
IXOM, Port Botany, Sydney
Sept15 - Ongoing
Scope of works:
Maintain lixators loading 24/7 – 352 days of year
Project Highlights:
Ensuring largest Chlorine producer in NSW constant supply of SALT with a 2hr max downtime
Caltex Refinery Project
Mar 18 - Aug 18
Scope of works:
Sorting and crushing of onsite demolition waste materials.
Project Highlights:
Successfully reduced our clients waste and provided cost savings as all crushed and processed materials were reused on site.
Nepean River Pedestrian Bridge
Dec 16 - Sept 18
Scope of works:
Sheet piling, drainage, detailed excavation, erosion & sediment control, landscaping
Project Highlights:
Extensive erosion controls were put in place to ensure minimal impact in the highly sensitive aquatic location.
Westmead Childrens Hospital, Sydney
Sept 16 - Jan 17
Scope of works:
Final Trim Grader work including ATS & Gen Plant hire
Project Highlights:
2 carparks graded to level on time and on budget for our client
Orica, Port Botany, Sydney
Oct 15 - Apr 16
Scope of works:
Building formation, drainage, steelworks, concreting, retaining walls, non destructive excavations, and asphalting.
Project Highlights:
Non destructive excavation service incoperated
Peats Ridge, NSW
Sept 19 - July 22
Scope of works:
Bulk earthworks, remove overburden, excavate rock for processing, material processing via trommels, build haul roads, heavy plant hire.
Project Highlights:
Working within a large quarry operating on mine site conditions.